Hi,
At the component overview screen, you can specify the required delivery date for each component.
That would be your planned delivery date for each component and can be seen report CN52N.
Coming to the project deliveries, on the project delivery screen system will bring up all the materials available in inventory. now select those items and delete them and save so system creates delivery for the items which are being remain on the delivery screen.
by doing this process you can have multiple project deliveries.
Thanks,
Sudhakar