hi Caetano,
The system is not changing the basic finish date, the system date is changing from Monday to Saturday when she is running the /md04 transaction i.e. from planned order to production order.
As I mentioned earlier, the in-house production time is "1" days. do you think it will change the end result,if we remove the "1" days.
Thanks,