Hi Jatin,
CN33 is used to replenish an assembly, which has a long replenishment lead time, before the design of the whole product is complete. First, you can transfer this assembly to Project System and generate preliminary requirements. So, this is used only for Operative networks and not for Standard Networks.
Regards,
Bala.